Status of the project: | Task | Description
| %done
| Estimated finish
|
|---|
SRAD technical design
| Technical description of the Software Defined Radio payload | 30% | 31/10/2008
| SRAD functional design
| Functional description of the Software Defined Radio payload. | 80% | 30/09/2008 | Mission analysis
|
The mission analysis has been made regarding to the 354 km x 1774 km (altitudes of perigee / apogee), 71º orbit, provided by Vega as the Xatcobeo deployment orbit. RAAN and argument of perigee are free parameters. | 100% | 31/08/2008 | Tools selection | Selection of the IT tools that will be used during the development of the project. | 100% | 25/8/2008
| | Servers provisioning and configuring | Provision, installation and configuration of all the IT resources needed to host the project.
| 100% | 1/9/2008
| Hiring the first developer group
| Hire the first developer group that will work on the main areas of the project.
| 80%